Article: Transmission Use Evident from Cycle Timing
Transmission Use Evident from Cycle
Timing
A three-phase
transmission line is an electrical model of a rotating shaft.
A drive shaft under heavy load will exhibit a small amount of torsion
between the power head and the load end. Similarly,
the load end of an electrical line will lag the generation end by a small but
measurable amount. The familiar
sine wave is representative of an AC voltage, and if an event recorder
monitoring voltage captures the exact time it rises through zero at the
generator while another event recorder captures the time at a load substation,
then both times can be compared (see Figure 1).
Measure Zero-Crossings
Figure 1
The difference between
the two times won’t translate directly to MWhs of flow, but it will be a
relative measurement based upon actual energy flow, line capacity, and distance.
The time difference will convey a wealth of system information when used
in conjunction with voltage measurements taken from the other substations in the
neighborhood.
In this way, this
article proposes to use voltage cycle timing to determine relative
transmission line loading. It is
based on the time differences in measured voltage events (zero-crossings of a
selected phase) at multiple locations across a synchronized system.
By accepting cycle timing as a metric, reliability coordinators would be
able to quantify power flow and transmission line strength by comparing single
instantaneous value per voltage level from different substations.
Furthermore, readings taken anywhere within the interconnected area would
be meaningful everywhere else regardless of region, control area, or state
borders.
To make sense of this,
a precision event recorder capable of time-stamping voltage events with
microsecond accuracy must be placed in every substation at every voltage level.
Each recorder, synchronized to Universal Time via GPS, reports the
time-stamp of selected cycles and submits them to a central web server.
The server receives and stores the information into a time-structured
database. Time, as the subject of
the metric, will be used in interesting ways.
Displays to
Represent Area Timing
The gathered
information, once received and stored, could be displayed in a geographic map of
substations and transmission lines. The
chronographic aspect could be shown as zones of difference where contour lines
clearly indicate bands of common cycle time difference.
See Figure 2 below where generator substations (labeled ‘G’) lead
other areas in bands of time difference. Visualize
the view to be similar to a contoured map showing elevation—in this case the
generators are the peaks and high plateaus while loads are ‘downhill’, or at
least down sloping, to valleys. The
actual course taken by the energy flow can be visualized as elevation drop
along transmission lines of the map, which is actually represented by time
difference through the many contour lines between substations.
Geographic/Chronographic Display
Figure 2
In this view, the
transmission line between Garrity and Columbia is intersected with no time
boundary contour lines while there are 3 contours on the line going South of
Garrity. This reveals that
relatively light loading exists between the two generators, but relatively heavy
loads reside to the South.
The display works
because a time-stamp measurement taken when voltage at the source crosses zero
always occurs ahead of the sink by a measurable amount.
What will be the time measurements where there are numerous generators
and loads distributed over the map? The
answer, obviously, is that the zones with greater generation will lead zones
with greater load. Due to the
physics of the electric system, all components will quickly seek their place in
time, and although still synchronized, will exhibit time differences that will
indicate the actual direction the energy flows.
Visibility of
Instability
Today, the electric
industry achieves and maintains 60Hz synchronization across the national power
grid using sophisticated methods involving generator control equipment.
However, the grid itself is far from being rock-solid stable.
It is influenced by every change of load and every change in generation. The energy behind the generators tries to speed-up rotational
frequency while the load tries to slow it down—all being held in check by
control equipment. In fact, the
entire interconnected grid exactly matches
Contour Shape Fluctuations Evident
Figure 3
generation to load.
Inadvertent differences are manifested in deviations of frequency away
from exact 60Hz. Too much
generation, the frequency rises above 60Hz—too much load, it drops below 60Hz.
With the grid operating like a roiling sea of turmoil, shifting contours
will highlight oscillations. Consider
Figure 3 in relationship to Figure 2. If
these two displays alternated separated by one or two seconds, it would reveal a
struggle between Garrity and Columbia generators.
This struggle would indicate system instability and consuming excess
generator fuel, capacity, and causing a certain amount of needless transmission
losses.
Timing Reference
This system is
dependent upon all substation sites to be precisely time-synchronized together.
Each site can do this using the timing features of the Global Positioning
System (GPS), which produces a synchronized and accurate timing pulse to sub-
microsecond accuracy to Universal Time regardless of world location.
Once synchronized, substation recorders can measure their time and report
the difference between it and the reference.
To establish a
universal reference, NERC could simply state that there shall be exactly 60
pulses per second with the first pulse arriving exactly at the 1-second mark.
This is not really a new concept; NERC has always worried about
frequency. But to establish a true
reference, there must be a start stating that this particular cycle is the
beginning, and from now on, all cycles will be based from it.
Thanks to the wandering nature of frequency, it is well known that such a
reference could lead or lag its intended place in time by multiple seconds.
Another possibility is
to allow the reference to be ‘in the clock of the beholder’.
In other words, a control area could monitor every substation inside
itself and declare the reference to be the leading measurement, and all other
measurements would be shown as time offsets from it.
Therefore, the leading generator has zero time difference and each other
substation lags it by a certain number of microseconds.
Since there are approximately 16,667 microseconds per cycle, each
degree of generator shaft rotation is 46.296 microseconds.
This measurement accuracy is well within measuring capability of
today’s synchro phasors and high-speed event recorders, and would certainly
provide adequate time bands from which to build map contours.
So Many
Measurements, So Little Time
The author has constructed event recorders with fast enough
time-stamping capability to verify the concepts purported herein.
The table below is a sample of recently captured time-stamps from two
substations separated by an estimated 18 miles (where ss=substation code, vvvv=voltage,
ssssss=Garmin seconds, mmmm=milliseconds, and uuuuu=number of 1/20
microseconds):
ss,vvvv,ssssss,mmmm,uuuuu
ss,vvvv,ssssss,mmmm,uuuuu
Diff uSec
------------------------- -------------------------
---- ----
V1,1537,529230,0065,05236
V2,1515,529230,0065,07376
2140 107
Although these measurements are anecdotal, the author
believes that the 107 uSec lag of substation V2 behind V1 indicates a robust
flow towards V2. (If the distance
between the two substations is 18 miles as believed, the voltage waveform should
exhibit a difference of about 96 uSecs accounting for the speed of light for the
voltage waveform to travel the distance. The fact that it took 11 uSec longer indicates a certain
amount of loading on the line.)
The information that would have been sent across a wide
area network for this single comparison would have amounted to a raw 25
characters per measurement. Inside
the central processor’s data storage, the time value for each substation could
be stored as the raw time reading and a difference value.
V1’s difference would store 0 (because it is the leading sub) and
V2’s difference would store 107 (because it is lagging the reference by 107
microseconds). Naturally, there
could be 60 of these stamps per second, and the database could store the
integrated difference as a single ‘average over a second’ integer.
Or, if desired, it could store 60 seconds as an integrated ‘average
over a minute’ integer. And, by
extension, hourly averages can be derived as well.
For making historical records, all the above may be desirable, and after
a few months of history is correlated with integrated MWh readings, future hours
could be forecast.
Conclusion: A New
Generation of Metering Equipment
This new time-stamping event recording meter along with its
data accumulator and contour map displays (patent pending) as proposed in this
article would be an inexpensive step in allowing all electric providers to make
lower voltage measurements and yet easily see the flow of system load as a
relative picture on a geographic/chronographic display.
Such a meter can be cheaply placed in a substation, connected to a
voltage device on a single phase, to a GPS receiver, and to the Internet.
It could transmit time measurements only, or add other available features
with small incremental costs. A web
server at the control center could handle the data accumulation and storage with
traditional time-oriented database applications and new software designed to
retrieve, sort, and replay captured events.
When future hour forecasts are made, E-Tag and pending schedule approvals
could be easily tested—just ensure that no Point-of-receipt to
Point-of-delivery path segments crosses too many contour lines!
Reliability centers
would desire this type of information to monitor system health in real time.
Marketers and power agents would desire this type of information to help
them schedule energy across transmission paths that exhibit few contour lines
crossing the path. The metric
information from around the nation could be sold to subscribers where they may
view regions in a real-time or historically integrated history display map. Such may help simplify decisions of energy scheduling and
help open competition in the electric industry.